Ridings - the Extension
This page shows the
Extension to the layout, commenced at the very end of 2006, and still being
developed in
2015! It had always been planned to
extend Ridings to give more operational variety, so when the railway was
originally
built points were installed to provide access to future boards like this one. Also, when the roads were built, the pointwork and the guide tracks were installed in readiness for this.
I had made a conscious
decision not to work on further boards until the original part of the layout was
more-or-less complete, because I found constructing baseboards and tracklaying
relatively easy, so I risked having lots of baseboards that were not
completed scenically. Furthermore, I
needed to know whether various things would actually work - like the trolleybus
overhead and the complex road system, and whether the scenery and buildings
would look right.
So, having effectively
finished the main boards, as described on the other layout pages - only a few more buildings remained, a
little scenic work, and some more trolleybus overhead - I decided to start on the
Extension. Another motivator for this was the fact that after a few Exhibitions it became
clear that the operation of the railway left a lot to be desired - with only one
track on the Branch, two-train operation was difficult and distracted me
from operating the roads. Therefore, as planned, the extension incorporates a two-track
main line and facility to add a fiddle yard for easier exchange of trains.
The extension was first 'mocked
up' with cardboard to ensure things fitted (see photos). The railway trackbed was then
laid and track-laying done properly. The wiring on the two boards was then completed, and
run back to the control panel, where the changes needed to reflect the new trackwork were
made. The point position indicators were upgraded from the home-made ones to Heathcote
Electronics memory type which remember the point position even when the power is
off. In addition the power supply was upgraded for the extra bus stop solenoids.
Work was finished with the roads in time to have the extension working for the
Sheffield Exhibition in June 2007, and afterwards continuing by making the
adjustments learned from that operation - quite a bit of work was required
'behind the scenes', and then a start was made on the structures that would
become the canal.
In a change of plan, during December 2007 DCC control was
added for the trolleybuses to avoid having to section the overhead to provide
individual control of each trolleybus - see 'Latest' Page.
Work continued on the canal sections and other scenery along with the road system to make the Extension ready for
exhibiting in 2008. About then I realised that the Extension is
almost as big as the original layout was, so I now understood why
it was taking me so long to build this extra section! After the Exhibitions,
things came to a standstill while I had to do other things (mainly to do with real
trolleybuses), but January 2009 saw work re-commence. I joined the
electronics group MERG and ordered some kits to build to operate my road points.
Seven of these were installed, covering all the points on the
Extension, in time for the Bradford Exhibition in April 2009. Eleven more have
since been added (see 'Latest' page).
Work continued after that on the scenery and the
trolleybus fleet with a view to having an improved layout at the Huddersfield
Railway Modeller's Exhibition in October 2010. The efforts were worthwhile as
Ridings won Best Layout in Show and some professional photos were taken for an
article for the Railway Modeller (published November 2011). These can be
seen here. Work, as always, carries on - the canal was finished for
example. The next major job was the street scene between the main layout and the
extension, along with a bit of scenic work in the same area. This took longer
than expected (doesn't it always?), but it was completed during early 2013, and
then the last bit of plasterwork scenery was finished butting up to this. In
2014/15 Walker's Nursery was added in the bottom right-hand corner - these days it would be called a
Garden Centre, but generally not in the 60's.
(>>) indicates a larger shot is available. Click on the arrows or the photo.
Board 6 with the road system. Obviously this has been mocked-up with straight bits of ply, and will eventually be sweeping curves. The large area on the left (covering a railway tunnel such that the trackwork seen here will not be on public view) will be a joint turning area for both roads, around some houses and shops. Further roads running off the edges will be tracked just in case I want to extend further, even though the room won't be big enough then! (>>) |
Back to Board 5 and the mock-up of the road system. There will be a canal in between the railway and the road in a dropped section to allow construction of a lock and some interesting bridges! (>>) |
Two shots with the trackbed constructed, cork underlay down and
painted, point motor holes cut and the track laid properly after preliminary checking for
correct geometry. These shots also show a couple of class 101 diesel multiple units
testing the track (using flying leads). |
Still required at this stage was all the necessary wiring to make it fully operational, but the general concept can now be seen properly. (>>) |
The wiring sockets between the boards and back to the control panel. Also shown is the essential microswitch on the point in the centre providing access to the reversing section. This is needed to switch the correct section into the reversing loop depending on the point setting. (>>) |
The control panel modified with the cab control lights and the point indicator lights on. The flying lead is for point switching. The reversing switch for the reversing section can be seen left-middle - the microswitch on the access point ensures that the reversing loop is powered from the correct main-line section. (>>) |
A row of terraces was already 'in stock' and this would be modified and then utilised along the new roadside which will be directly in front of these. The sweeping curve past these falls and then rises again as well, so the road had to match the contours of the row of houses. To the right of that you can see the dropped section which will become the canal, before reaching the railway embankment. (>>) |
(>>) | (>>) Two shots after the guide slots had been routed. I have provided several 'holding areas' for vehicles, so that they can be waiting in the wings, not blocking the main roads. The road system has been made quite complex, as once everything's laid you can't change your mind and add bits! However, I did decide to add an extra link after experience at the 2007 Sheffield Exhibition - see below. Some holding tracks run off the edges in case I want to extend again. |
The extension boards assembled away from the main layout so I could work on all sides. Here the roadway supports have been constructed so that the slopes coincide with the existing housing module (now tided up), and the guideway grooves have been routed. The narrow channel for the canal is more apparent now. (>>) |
Guide wires inserted, and the essential points made operational. (>>) |
Temporary roadway laid to enable testing with one of the Huddersfield motorbuses. All successful so far! The extension was therefore ready for operation at
the the Sheffield Exhibition on the 23rd June 2007 - see photos on the main Ridings page. |
The control panel updated with the road mimic diagram. As the bus stops had not been fitted at this stage, there are no switches yet for these. The space at the bottom was for further controllers, but these have been superseded by adopting DCC control - see 'Latest' Page for information on the DCC additions. (>>) |
Work after the 2007 Exhibition
continued, initially to sort out problems discovered at the Exhibition, or finishing jobs
that were left over from before it. These included: improving the board connections to make them more level, adding the short 'fiddle board' to the bottom of the picture on the right, inserting the remaining guide wires to the board edges, finishing the points and control wires, and laying a new link past the bus stop on the main board. It was discovered that this was required as vehicles returning by the short route to town could not get past a parked vehicle at the right-hand bus stop (see right). The rail joints have now been strengthened, so the next jobs are to start on the structure of the scenery, paint and ballast the track, and sort out the tunnel entrance. |
The track modification mentioned on the left can be seen here, linking the upper road to the passing loop down the centre. Yes, its all pretty complex! (>>) |
This picture shows the other, smaller, board with its point control wires. The scissors crossover is to enable the parking of vehicles in the siding with other vehicles arriving or setting off past them. The road bridge design was the next to be worked out - it was complicated by the canal. This occupies the 'slot' between the railway and the road, then snakes under the railway. In the picture on the right the canal floor and banks have been laid, and a retaining wall and a bridge have been constructed. Obviously all this still needs cladding with walling etc. (>>) |
Here with the track weathered, all the retaining walls in place, and the two railway bridges created. The area at the front will become grass banking. The road bridge has been started but still requires side-walls. It can now be seen that the road crosses the railway and the canal at the same time - a triple-layer bridge! (>>) |
A view through the three-tier bridge. (>>) |
Turning to the other end, the railway tunnel entrance saw some work, as did the retaining walls, and the canal basin floor. The canal lock will be in the dropped section to the left. The canal finishes at Tunnel End! The canal will disappear into a tunnel here, just as the Huddersfield Narrow Canal does at Marsden. (>>) |
The canal lock starts to make an appearance -the basic lock walls have been surfaced. The bridge connecting the main road with the track that dives under the railway has also been constructed. There are a lot of walls to clad to finish this section! (>>) |
The roadway at the top gets its bridge sides. This is a Wills kit which has been modified to suit the slope and extra length of this bridge. A canal bridge is required for a minor road here, so another Wills kit has been used. Most canal bridges in the locality were tapered towards the middle and it has been 'skewed' to suit the diagonal nature of the crossing. (>>) |
.A view from the other side of the bridges with the stonework being applied. (>>) |
Attention turns to the other Extension board, and the canal walling gets cladded, with the tunnel entrance being picked out for the first time. The canal bridge still needs to be arched into place - I'm waiting until it won't be in the way. (>>) |
An unusual view from the end showing the lock preparations and the two tunnel mouths. The bridge and lock gates still need installing. (>>) |
A long view with the walling finished but not painted. (>>) |
An atmospheric shot along the canal, looking into the lock throat. The canal tunnel can be made out in the distance. (>>) |
The railway track is now ballasted - a very tedious job, but you have to do it eventually! The loop has been 'ash ballasted' while the main lines are regular granite. This board now requires it's hillsides at the front - mainly on the left hand side, to blend in the roadways and the trackbed.
|
The extension boards needed their bus stop solenoids fitting - these were put on order while the switches for them were fitted and wired up. This shot also shows the Trix DCC controller. After the solenoids arrived they were fitted and wired back to the control panel. (>>) |
All the walls weathered and a start has been made on making the canal look abandoned. Compare with the picture above. The roadway still needs its covering of 'asphalt', which could not be applied until after the solenoids had been fitted and tested. (>>) |
A shot from above the tunnel mouth along the railway and canal. (>>) |
The extension in use at the Sandtoft Model Weekend 2008. Compare with the previous picture. (>>) |
Christmas 2008 was a time for reflection. The road points were awkward at exhibitions as you had to be in the right place to operate them, and it was difficult to tell which way they were set. Also Board 5 required 4 across-board links for the rods, which wasn't very practical. I studied various ways of DCC-ing them (I didn't want to use DC methods as this would have required umpteen more wires), but all methods were expensive and meant that you had to remember lots of numbers to key in. Then a colleague told me that MERG did a set of kits so that you can run points from panel switches, and then this was encoded into DCC and you used normal accessory decoders to drive the points. I joined MERG and ordered some kits. While waiting for them to arrive, I added supports to Board 5 for the motors and mounted the first one. I plan to leave the operating rods in place so that I can still use them in emergency. |
Photo of the arrangements taking shape on Board 5. The first point motor is on the left and the point can be seen in the foreground. I had to 'dig the road up' as the point itself had broken, and I also needed to alter the rightmost curve as buses hit the wall coming round it. (>>) |
All 4 point motors fitted to Board 5 now. Here are 3 of them, along with the built MERG DCC Decoder (not in its final resting place). Board 6 had yet to be dealt with. (>>) |
The Decoder board fitted under the roadway supplying the four point motors on this part of the layout. (>>) To the right is a shot of the seven point switches in place (4 for Board 5, 3 for Board 6). The MERG Encoder is of course inside this panel. (>>) |
|
Meanwhile, the backs of the long row of houses was being detailed, having previously been plain plasticard. The formers are also installed ready for the scenery here, which will be a banking forming a natural break between the town and the canal area. (>>)
|
This is a shot taken at the Bradford Exhibition in April 2009, showing the grassy bank now in situ behind the row of houses. More pictures from the Exhibition can be found on the main page. (>>) |
Due to my having far too much to do, I have commissioned a housing module to be built by another modeller. This is the central section at the Extension's terminus (above), so it was particularly convenient to provide him with the base-board that fits the hole. Meanwhile I worked on the houses in front of this, the short row of elderly terraces in the right-hand corner was the first to be finished. |
The 3-storey corner group after detailing the back yard and adding steps and a gas lamp on the wall. (>>) |
The same block from the front, with the pub "The White Lion" at the side. (>>) The next job will be fitting pavements. |
A different back view showing that the housing module behind has also been detailed - gas lamps and a washing line can be seen. (>>) |
Pavement work has been going on, as shown in the two shots here of the central block of houses and shops (above and right). (>>) |
Whilst I don't like doing the pavements, they do help to finish off the street scenes. Compare with photo above. (>>) |
Meanwhile, the canal is receiving attention. A maintenance barge has been built, the bridge is ready to be added when the water has been poured in, and the lock gates are under construction. (>>) |
The canal lock gates constructed from a Craftline kit (as was the barge). (>>) |
The gates are painted and ready for installation. (>>) |
The gates installed and the bridge finished. (>>) |
Water and 'junk' have been added to the lock to complete the picture. (>>) |
The rest of the canal needed to be treated the same way as
the lock. The theory is that the local Canal Society have made a start on
restoring the canal, but so far have only managed to clear the weeds from
the very top section, refurbished a maintenance barge and painted the lock
gates. Many years of clearing junk, weeds and accumulated silt would be
required before the canal would be navigable again. Thus the lower stretch
of the canal is still filled with foliage and debris. |
The bridge end of the canal with Huddersfield, Halifax, Bradford and Hebble buses in view. A slow 'up' coal train runs alongside the passing loop while a Transpennine is going the other way. (>>) |
Closer detail of this end of the canal with a Transpennine set thundering through the bridge whilst a Bradford bus passes above. (>>) |
The first building on the main shopping street is a Yorkshire Penny Bank. Next door is a Stationers with Prudential Assurance above. Next to be constructed will be some mock-Tudor shops. (>>) |
The scratch-built Tudor block completed apart from the roof, and ready to install next to the Stationers. I'm pleased with the result. (>>) |
The Tudor shops installed - this is the first of 3 sub-bases finished which will form the main street. (>>) |
Another view taking in more of the surroundings. Next will be a corner shop, probably a café. (>>) |
The completed café, actually called a tearoom, shown from the other end. (>>) |
A front view, looking up the opposite street. (>>) |
The next two buildings are to be a larger shop and then an arcade (nearest one). These are positioned to check for fit before painting and assembling. The larger shop will complete the second sub-base and the arcade will start the third and last one. |
The large shop completed. This has become 'Rushworths' which
was a large Huddersfield Department Store at the time. A narrow lane between
it and the tearooms provides access to the rear of the shops. |
A view along the rear of the shops at this stage. |
The next building - a shopping Arcade - is taking shape and will be followed by an end shop. |
The end shop now finished - note this one has closed down and therefore empty. Next door will be a partially demolished building. (>>) |
The demolition site completes the last section. Part of the unfinished bit of scenery can be seen behind. (>>) |
The remaining plasterwork for the scenery on both sides of the lane is finished off and Autumnal foliage and pavements added. (>>) |
|
The walls weathered and Greenhouses constructed. One of the smaller ones will be used on a housing development elsewhere. |
The finished corner, which makes quite a nice busy scene. The railway cable troughing has since been finished in this area. (>>) |
The area with the signal box and its associated cable trunking in place. (>>) |
return to main Ridings page | Layout - Early | Layout - Development | Vehicles |